title: Monthly Report on Activities of Decentralized Climate Foundation A.C. February 2023.
|
||||
author: Omar Octavio Huerta Valdez
|
||||
date: 2023-05-10
|
||||
layout: post
|
||||
---
|
||||
|
||||

|
||||
|
||||
Created: **5th March 2023**
|
||||
|
||||
|
||||
## :beginner: Introduction.
|
||||
This monthly report aims to provide an overview of the activities, projects, and finances of the Decentralized Climate Foundation A.C. Through this document, we seek to inform our members and collaborators about the achievements and challenges we faced during the month. Furthermore, we aim to provide transparency and accountability regarding the use of resources and progress towards our long-term goals. This report includes details on the activities carried out, the status of ongoing projects, financial analysis, and future planning.
|
||||
|
||||
|
||||
## 📈 Activities carried out.
|
||||
|
||||
The activities for the month of February were divided into 4 main divisions that are subdivided into specific tasks, which are as follows:
|
||||
|
||||
### **Community.**
|
||||
|
||||
**February 2nd, 3rd, and 4th.** The Decentralized Climate Foundation community attended the Solana Etherfuse Hackathon, participating enthusiastically to promote the Foundation's activities, as well as trying to win the competition with a revolutionary and innovative project about better management of pensions for senior citizens.
|
||||
|
||||

|
||||
Img. 1 At the facilities of the central auditorium of the Interdisciplinary Professional Unit of Engineering and Advanced Technologies of the National Polytechnic Institute.
|
||||
|
||||

|
||||
Img. 3 At the facilities of the computer center of the Interdisciplinary Professional Unit of Engineering and Advanced Technologies of the National Polytechnic Institute, about to start the project.
|
||||
|
||||

|
||||
Img. 3 At the facilities of the computer center of the Interdisciplinary Professional Unit of Engineering and Advanced Technologies of the National Polytechnic Institute, about to start the project.
|
||||
|
||||
|
||||

|
||||
Img. 5 "Leaving the facilities of the computer center of the Interdisciplinary Professional Unit of Engineering and Advanced Technologies of the National Polytechnic Institute, concluding our participation."
|
||||
|
||||
|
||||
The link to the event can be consulted in Annexe 1.
|
||||
|
||||
|
||||
### **R&D Phase 1 DAO.**
|
||||
|
||||
**February 16th.** The Decentralized Climate Improvement Proposal (DCIP-02) is delivered, which is the proposal to standardize the methodologies of the Board of Directors' calls to address various topics of interest to the Foundation, such as progress in members' tasks, news with procedures, financial statements, and for general news that may arise. This proposal is delivered by the Foundation's spokesperson and lead developer.
|
||||
|
||||
The document can be consulted in Annexe 2.
|
||||
|
||||
|
||||
### **Administration.**
|
||||
|
||||
**February 9th.** The necessary cards are generated for the Foundation members in the FINTECH Albo. Basically for the collaborators Alfonso Nuñez (Treasurer) and Gustavo Bermudez (Student providing Social Service). The President is the one who carried out the procedures for these cards.
|
||||
|
||||
Also on this day, the Monthly Report of January of the Decentralized Climate Foundation is submitted for analysis and approval to the Board of Directors.
|
||||
|
||||
The monthly report can be found in Annexe 4.
|
||||
|
||||
**From February 10th to 25th.** The respective administrative tasks that are recurring in nature, such as paying for maintenance of the Foundation's facilities, attending to cleaning and maintenance personnel, and various charges for services, among other activities, are carried out.
|
||||
|
||||
**February 24th.** The formal process of linking with LaSalle University Cancun campus begins, so that students from that educational institution can carry out social service, professional stays, professional internships, and research at the Decentralized Climate Foundation. The Treasurer of the Foundation, Alfonso Navarro Nuñez, is leading these negotiations.
|
||||
|
||||
**27th February.** On the 27th of February, the First General Assembly of Associates was held where various additions and modifications were made to the Articles of Incorporation of the Decentralized Climate Foundation, such as the admission of new members Omar Octavio Huerta Valdez, Alfonso Nuñez Navarro, Francisco Sandoval, and Christian Sandoval.
|
||||
|
||||
Likewise, several provisions regarding the commercial and fiscal management of the Foundation were modified, and the resignation of Director Alberto Saavedra was formally accepted to form the new management body that took office.
|
||||
|
||||
The Assembly Minutes #1 can be found in Annexe 3.
|
||||
|
||||
### **Maintenance.**
|
||||
|
||||
In this section, maintenance activities are carried out on the main infrastructure of the Foundation, such as servers, computer equipment, and other electronic devices that the Foundation uses for its daily operations.
|
||||
|
||||
The two main developers of the Foundation actively participate in these activities.
|
||||
|
||||
As a noteworthy mention of these regular tasks, it is worth noting the training provided to Treasurer Mr. Alfonso Navarro Nuñez by Vocal David E. Perez, so that he could understand the technological infrastructure and make use of it.
|
||||
|
||||
### **DCF MaxCoin Mining and IPFS Node Increase.**
|
||||
|
||||
**10th to 12th February.** During these days, the Vocal David E. Perez was tasked with installing, testing, and operating the cryptocurrency miners that were donated by members of the MaxCoin community and the Decentralized Climate Foundation. Along with experts in electronic engineering, they undertook this activity.
|
||||
|
||||
## :moneybag: Finance.
|
||||
|
||||
The Finance section can be found in Annex 5, which details the income, expenses, and expenditures made by the foundation throughout the month.
|
||||
|
||||

|
||||
|
||||
## :clipboard:Current Projects.
|
||||
|
||||
In this section, we showcase the projects we are currently involved in.
|
||||
|
||||
We are currently working with our first intern, who is helping us with the documentation of internal processes of the Foundation.
|
||||
|
||||
They have satisfactorily completed various courses and workshops that have been imparted to them in order to understand the internal processes of the Foundation, so they can start the process of maintaining the technological infrastructure.
|
||||
|
||||
They were given courses and workshops on Git and version control using Github, Gitflow, and an introduction to Web3, IPFS, and other tools.
|
||||
|
||||
We are also reviewing the financial situation with the Board of Directors to make the best economic decisions while we are resolving the paperwork with the Mexican federal government.
|
||||
|
||||
## :pencil:Future goals and objectives.
|
||||
|
||||
The Foundation has several projects and objectives that it plans to carry out in the future. One of them is the DECA 2 project, which consists of updating diagrams and documentation by NSI to request an economic stimulus from CONACyT. This project includes the elimination of carbon credits from cryptocurrency processes, updating MVP information, updating the working model between NSI and the Foundation, and creating an agreement between DCF and NSI.
|
||||
|
||||
Another project that the Foundation has in mind is the IHS company's MVP, for which necessary information is being researched to develop it.
|
||||
|
||||
Additionally, the Foundation is working on financing options, where there are two viable options: CLUNI and CONACyT scholarship. Both are government agencies, but they have different procedures and the Foundation plans to use them to obtain resources for technological development.
|
||||
|
||||
These are some of the projects that the Foundation has planned for the future and expects to complete in the coming months.
|
||||
|
||||
## 🎯 Conclusions and Recommendations.
|
||||
|
||||
In summary, over the course of February we have made significant progress in achieving the objectives of our foundation. We conducted fundraising activities and identified opportunities to improve our internal management. Additionally, we organized and updated our donor database.
|
||||
|
||||
Regarding recommendations, we consider it crucial to continue working on fundraising to finance current projects and to improve efficiency in managing the foundation's resources to maximize its impact. Finally, we suggest continuing to update and organize the donor database, which will allow for more effective and long-lasting relationships with our collaborators.
|
||||
|
||||
In conclusion, we believe that this month has been very productive for our foundation and we are confident that by following these recommendations, we can achieve our short- and long-term objectives.
|
||||
## :beginner:Annexes.
|
||||
|
||||
1. https://hackathon.etherfuse.com/
|
||||
2. https://hackmd.io/c-0PvrXFQWezOJpzNtRA1A?view
|
||||
3. https://nextcloud.neetsec.com/index.php/s/EaXWH8t3GpyMS9R
|
||||
4. https://hackmd.io/bcSkwAWZQCihO-1G7eQGZg
|
||||
5. https://nextcloud.neetsec.com/index.php/s/MbSsF52fNMwsDp3
|
||||
|
||||
Created by Omar Octavio Huerta Valdez.
|
|
@ -1,5 +1,5 @@
|
|||
---
|
||||
title: Monthly activity report of the Decentralized Climate Foundation A.C. January.
|
||||
title: Monthly Activity Report of the Decentralized Climate Foundation A.C. January.
|
||||
author: Decentralized Climate Foundation
|
||||
date: 2023-05-10
|
||||
layout: post
|
||||
|
|
|
@ -0,0 +1,109 @@
|
|||
---
|
||||
title: Monthly Report on Activities of Decentralized Climate Foundation A.C. March 2023.
|
||||
author: Omar Octavio Huerta Valdez
|
||||
date: 2023-05-10
|
||||
layout: post
|
||||
---
|
||||
|
||||

|
||||
|
||||
Created: **5th April 2023**
|
||||
|
||||
|
||||
## :beginner: Introduction.
|
||||
This monthly report aims to provide an overview of the activities, projects, and finances of the Decentralized Climate Foundation A.C. Through this document, we seek to inform our members and collaborators about the achievements and challenges we faced during the month. Furthermore, we aim to provide transparency and accountability regarding the use of resources and progress towards our long-term goals. This report includes details on the activities carried out, the status of ongoing projects, financial analysis, and future planning.
|
||||
|
||||
|
||||
## 📈 Activities carried out.
|
||||
|
||||
The activities for the month of February were divided into 4 main divisions that are subdivided into specific tasks, which are as follows:
|
||||
|
||||
### **Social Services.**
|
||||
|
||||
**Throughout the month of March**, we worked hard with the student providing Social Service in their training program, which is mainly focused on learning Web3 for the update and maintenance of the foundation's website. The courses on Web3 are taught by David Eugenio Perez Negro Rocha, who also presented the achievements and progress of the project with the Social Service student. The Web3 Static workshop can be found in Annexe 1.
|
||||
|
||||
The website and progress to date can also be consulted in Annexe 2.
|
||||
|
||||
**Throughout the month of March**, We also delivered the final results of the introductory courses and workshops from February, such as the Git and Github Version Control Course, which are fundamental for the proper understanding of processes with Web3.
|
||||
|
||||
These courses covered basic topics such as initializing repositories, cloning, hosting in local repositories, performing pull, push, and updating repositories.
|
||||
|
||||
We also worked on learning GitFlow, which is basically the application of Git knowledge for the decentralization of the foundation's websites.
|
||||
|
||||
The deliverables can be consulted in Annexe 3.
|
||||
|
||||
**Throughout the month of March**, We also introduced the Social Service student to the use of Artificial Intelligence with the aim of introducing them to it, familiarizing them with it, and supporting them in its use for their tasks. This was done with the aim of finding more efficient and automated ways of carrying out tasks, reducing time and costs, and maximizing the effectiveness of both the student and the foundation's work and processes.
|
||||
|
||||
The deliverables can be consulted in Annexe 4.
|
||||
|
||||
Throughout the month of March, we also made the final delivery of the UML diagram creation course documentation, so that the Social Service student would have knowledge of Software Engineering in order to initiate the development of the IHS company's MVP project, belonging to David Eugenio Perez Negron, and with which we seek to link the Decentralized Climate Foundation to this development. The student developed class UML diagrams that are fundamental in Software Engineering for their understanding and future application.
|
||||
|
||||
The deliverables can be consulted in Annexe 5.
|
||||
|
||||
|
||||
### **R&D Phase 1 DAO.**
|
||||
|
||||
**On February 16th**, the Decentralized Climate Improvement Proposal (DCIP-02) was submitted to standardize the methodologies for the Board of Directors' calls to discuss various topics of interest to the Foundation, such as progress reports from members, updates on administrative procedures, financial statements, and general news. The proposal was submitted by the Foundation's Vocal and principal developer.
|
||||
|
||||
The document can be consulted in Annexe 6.
|
||||
|
||||
### **Administration.**
|
||||
|
||||
**From March 10th to 25th**, The corresponding administrative tasks were carried out, such as paying for maintenance of the Foundation's facilities, coordinating with cleaning and maintenance staff, and various other service-related activities.
|
||||
|
||||
**On March 18th and 19th**, The first meeting was held with a potential accountant for the Decentralized Climate Foundation to have a professional who could handle administrative procedures with the Mexican tax authorities. Negotiations were conducted to establish a service contract with the accounting firm Tafolla & Associates. Once the agreement was reached, the President of the Decentralized Climate Foundation made initial contact with Mr. Pedro Tafolla, the firm's principal accountant. The Treasurer, Alfonso Navarro, and the Vocal, David Eugenio Perez Negron, were mainly involved in this activity.
|
||||
|
||||
### **Maintenance.**
|
||||
|
||||
In this section, maintenance activities are carried out on the main infrastructure of the Foundation, such as servers, computer equipment, and other electronic devices that the Foundation uses for its daily operations.
|
||||
|
||||
The two main developers of the Foundation actively participate in these activities.
|
||||
|
||||
As a noteworthy mention of these regular tasks, it is worth noting the training provided to Treasurer Mr. Alfonso Navarro Nuñez by Vocal David E. Perez, so that he could understand the technological infrastructure and make use of it.
|
||||
|
||||
## :moneybag: Finance.
|
||||
|
||||
The Finance section can be found in Annexe 7, which details the income, expenses, and expenditures made by the foundation throughout the month.
|
||||
|
||||

|
||||
|
||||
## :clipboard:Ongoing Projects.
|
||||
|
||||
In this section, we showcase the work we are currently involved in.
|
||||
|
||||
Currently, we are working with the First Social Service who are helping us document the organization's internal processes.
|
||||
|
||||
They have successfully completed various courses and workshops to understand the DCF's internal processes to start maintaining the technological infrastructure in optimal conditions and delegate more responsibilities.
|
||||
|
||||
They have attended courses and workshops on Git and version control on Github, Gitflow, and have also learned about Web3, IPFS, and other tools.
|
||||
|
||||
Finances remain a delicate topic that the H. Board of Directors continues to work on to ensure that the government procedures that the Foundation is undergoing can be concluded as soon as possible.
|
||||
|
||||
## :pencil:Future Goals and Objectives.
|
||||
The Foundation has a series of projects and objectives it aims to achieve in the future. One of them is the DECA 2 project, which involves updating the NSI diagrams and documents to request from CONACyT. This project includes the removal of carbon credits from cryptocurrency processes, updating MVP information, updating the working model between NSI and the Foundation, and creating an agreement between DCF and NSI.
|
||||
|
||||
Another project that the Foundation has in mind is the IHS MVP, which is currently researching the necessary information for its development.
|
||||
|
||||
In addition, the Foundation is working on financing options, two of which are possible: the government program CLUNI and the CONACyT scholarship. Both are government agencies, but they have different procedures, and the Foundation plans to use them to acquire resources for technological development and its operation as such.
|
||||
|
||||
These are some of the projects that the Foundation has planned for the future and intends to carry out in the coming months.
|
||||
|
||||
## 🎯 Conclusions and Recommendations.
|
||||
|
||||
In summary, during the month of March, we made significant progress in achieving the objectives of the platform. We carried out fundraising activities and identified opportunities to improve our internal governance. Additionally, we organized and updated our donor database.
|
||||
|
||||
Regarding recommendations, we believe it is important to continue seeking funds to finance ongoing projects and improve efficiency in managing fund resources to maximize impact. Finally, it is recommended to continue updating and organizing our sponsor database, which will help establish a more productive and lasting relationship with our partners.
|
||||
|
||||
In summary, we believe that our platform has been very successful this month, and we are confident that by following these recommendations, we will be able to achieve our short and long-term goals.
|
||||
|
||||
## :beginner:Annexes.
|
||||
|
||||
1. https://hackmd.io/gbfcNdtPTNy4jz60-8Fqpw?view
|
||||
2. https://decentralizedclimate.org
|
||||
3. https://hackmd.io/ARL7nmX7TL2f1FvKKx4olg?both
|
||||
4. https://hackmd.io/5TTxd6x6Qdi9pzRkFq6T7A
|
||||
5. https://hackmd.io/LKrbBs0JSDe0fY25IJ9cjg
|
||||
6. https://hackmd.io/c-0PvrXFQWezOJpzNtRA1A
|
||||
7. https://nextcloud.neetsec.com/index.php/s/MbSsF52fNMwsDp3
|
||||
|
||||
Created by Omar Octavio Huerta Valdez.
|
|
@ -0,0 +1,117 @@
|
|||
---
|
||||
title: Informe Mensual de Actividades de la Decentralized Climate Foundation A.C. Marzo 2023.
|
||||
author: Omar Octavio Huerta Valdez
|
||||
date: 2023-05-10
|
||||
layout: post
|
||||
---
|
||||
|
||||

|
||||
|
||||
|
||||
**5 de Abril de 2023**
|
||||
|
||||
## :beginner: Introducción.
|
||||
|
||||
Este informe mensual tiene como objetivo proporcionar una visión general de las actividades, proyectos y finanzas de la Asociación Civil de la Fundación Climática Descentralizada. A través de este documento, buscamos informar a nuestros miembros y colaboradores sobre los logros y desafíos que enfrentamos durante el mes. Además, esperamos proporcionar transparencia y rendición de cuentas sobre el uso de recursos y el progreso hacia nuestros objetivos a largo plazo. Este informe incluye detalles sobre las actividades realizadas, el estado de los proyectos en curso, un análisis financiero y la planificación futura.
|
||||
|
||||
|
||||
## 📈 Actividades realizadas.
|
||||
Las actividades del mes de marzo se dividieron en 4 divisiones principales que se subdividen en tareas específicas, que son las siguientes:
|
||||
|
||||
### **Servicios Sociales.**
|
||||
|
||||
**Todo el mes de marzo.** Se trabajó arduamente con el alumno prestador de Servicio Social en su programa de capacitación que está enfocado principalmente en el aprendizaje de Web3 para la actualización y mantenimiento de la pagina de internet de la fundación. El encargado de impartir los cursos de Web3 es el vocal David Eugenio Perez Negro Rocha quien a su vez expuso los logros obtenidos y los avances del proyecto con el alumno de Servicio Social. El taller de Web3 Static puede ser encontrado en el anexo 1.
|
||||
|
||||
La pagina web y los avances al día de hoy pueden ser tambien consultados en el anexo 2.
|
||||
|
||||
**Todo el mes de marzo.** De igual manera se entregaron los resultados finales de los cursos y talleres introductorios del mes de febrero como son el Curso de Control de Versiones en Git y Github, fundamentales para el correcto entendimiento de los procesos con Web3.
|
||||
|
||||
En estos cursos se tocaron temas básicos como la iniciación de repositorios, su clonación, el alojamiento en repositorios locales, realizar pull, push, actualizar repositorios.
|
||||
|
||||
De igual manera se trabajó en el aprendizaje de GitFlow que es básicamente la aplicación de los conocimientos de Git para la realización de la descentralización de las paginas web de la fundación.
|
||||
|
||||
Los entregables pueden ser consultados en el anexo 3
|
||||
|
||||
**Todo el mes de marzo.** Así mismo se dio la introducción al uso de Inteligencia Artificial al alumno prestador de Servicio Social con la finalidad de que se introdujera en su uso, se familiarizara y se apoyara en ella para la realización de sus tareas. Esto con la finalidad de encontrar formás más eficientes y automatizadas de realizar las tareas para que, entre muchas cosas, se redujeran los tiempos, los costos y se maximizara la efectividad tanto del alumno como de los trabajos y procesos de la fundación.
|
||||
|
||||
Los entregables pueden ser consultados en el anexo 4.
|
||||
|
||||
**Todo el mes de marzo.** Por ultimo y por esto no menos importante se realizó la entrega final de la documentación del curso de creación de diagramas UML esto con la finalidad de que el alumno prestador de Servicio Social tuviera conocimientos de Ingeniería de Software con la finalidad de iniciar los desarrollos del MVP de la empresa IHS, proyecto perteneciente al vocal David Eugenio Perez Negron y con el cual se busca vincular a la Decentralized Climate Foundation con este desarrollo. El alumno desarrolló diagramas UML de clases que son fundamentales en la Ingeniería de Software para su comprensión y futura aplicación.
|
||||
|
||||
Los entregables pueden ser consultados en el anexo 5.
|
||||
|
||||
### **R&D Phase 1 DAO.**
|
||||
|
||||
**16 de febrero.** Se entrega el Propuesta de Mejora para la Decentralized Climate por sus siglas en inglés (DCIP-02) Decentralized Climate Improvement Proposal la cual es la propuesta para estandarizar las metodologías de llamadas del Consejo de Administración para tocar diversos temas de interés de la Fundación, tales como avances en las tareas de los integrantes, novedades con tramites, estados financieros y para noticias en general que surjan. Esta propuesta es entregada por el Vocal de la Fundación y principal desarrollador.
|
||||
|
||||
El documento puede ser consultado en el anexo 6.
|
||||
|
||||
|
||||
### **Administración.**
|
||||
|
||||
**Del 10 al 25 de marzo.** Se realizan las respectivas tareas administrativas que son de caracter recurrente como realizar los pagos de mantenimiento de las instalaciones de la Fundación, la atención con el personal de limpieza y mantenimiento de las instalaciones, cargos diversos por concepto de servicios entre otras actividades.
|
||||
|
||||
**Del 18 y 19 de marzo.** Se realiza el primer encuentro con el posible contador de la Decentralized Climate Foundation esto con el fin de contar con una persona profesional que pueda realizar los tramites ante las autoridades hacendarias mexicanas. Se realiza la negociación de un contrato de servicios por parte del despacho de contabilidad Tafolla & Asociados. Quedando cerrado el trato se realiza el primer contacto entre el Presidente de la Decentralized Climate Foundation y el Lic. Pedro Tafolla, contador principal del despacho de contabilidad anteriormente mencionado. En esta actividad participaron principalmente el Sr. Tesorero Alfonso Navarro y el Sr. Vocal David Eugenio Perez Negron
|
||||
|
||||
### **Mantenimiento.**
|
||||
|
||||
En esta sección se llevan a cabo actividades de mantenimiento en la infraestructura principal de la Fundación, como servidores, equipos de computación y otros dispositivos electrónicos que la Fundación utiliza para su operación diaria.
|
||||
|
||||
Los dos principales desarrolladores de la Fundación participan activamente en estas actividades.
|
||||
|
||||
Como mención destacable de estas tareas regulares se menciona la capacitación que se le impartió al Sr. Tesorero Alfonso Navarro Nuñez por parte del Vocal David E. Perez para que pudiera entender la infraestructura tecnologica y así mismo hacer uso de ella.
|
||||
|
||||
## :moneybag: Finanzas.
|
||||
|
||||
La sección de Finanzas se encuentra en el Anexo 7, el cual detalla los ingresos, gastos realizados por la fundación a lo largo del mes.
|
||||
|
||||

|
||||
|
||||
## :clipboard:Proyectos en curso.
|
||||
|
||||
En esta sección mostramos el trabajo en el que estamos involucrados actualmente.
|
||||
|
||||
|
||||
Actualmente estamos trabajando con el Primer Servicio Social quienes nos están ayudando a documentar los procesos internos de la organización.
|
||||
|
||||
Ha realizado satisfactoriamente los diversos cursos y talleres realizados para conocer los procesos internos de la DCF para poder empezar a mantener la infraestructura tecnológica en optimas condiciones y poderle delegar mayor número de responsabilidades.
|
||||
|
||||
|
||||
Ha asistido a cursos y talleres sobre Git y control de versiones en Github, Gitflow y también aprendió sobre Web3, IPFS y otras herramientas.
|
||||
|
||||
Las finanzas siguen siendo un tema delicado que el H. Consejo de Administración sigue trabajando para lograr que los tramites gubernamentales que la Fundación está realizando puedan concretarse lo más pronto posible.
|
||||
|
||||
## :pencil:Metas y objetivos futuros.
|
||||
|
||||
La Fundación tiene una serie de proyectos y objetivos que pretende alcanzar en el futuro. Uno de ellos es el proyecto DECA 2, que consiste en actualizar los diagramas y documentos de NSI para requerir al CONACyT. Este proyecto incluye la eliminación de créditos de carbono de los procesos de criptomonedas, la actualización de la información de MVP, la actualización del modelo de trabajo entre NSI y la Fundación, y la creación de un acuerdo entre DCF y NSI.
|
||||
|
||||
|
||||
Otro proyecto que tiene en mente la Fundación es el MVP de IHS, el cual actualmente se encuentra investigando la información necesaria para su desarrollo.
|
||||
|
||||
|
||||
Además, la Fundación está trabajando en opciones de financiamiento, de las cuales dos son posibles: el programa gubernamental CLUNI y la beca CONACyT. Ambas son agencias gubernamentales, pero tienen procedimientos diferentes y la Fundación planea usarlas para adquirir recursos para el desarrollo tecnológico y su para su funcionamiento como tal.
|
||||
|
||||
|
||||
Estos son algunos de los proyectos que la Fundación tiene previstos para el futuro y prevé realizar en los próximos meses.
|
||||
|
||||
## 🎯 Conclusiones y recomendaciones.
|
||||
|
||||
En resumen, durante el mes de marzo avanzamos significativamente en el logro de los objetivos de la plataforma. Realizamos actividades de recaudación de fondos e identificamos oportunidades para mejorar nuestro gobierno interno. Además, organizamos y actualizamos nuestra base de datos de donantes.
|
||||
|
||||
|
||||
En cuanto a las recomendaciones, creemos que es importante seguir buscando fondos para financiar los proyectos en curso y mejorar la eficiencia en la gestión de los recursos del fondo para maximizar su impacto. Finalmente, se recomienda continuar actualizando y organizando su base de datos de patrocinadores, lo que ayudará a establecer una relación más productiva y duradera con nuestros colaboradores.
|
||||
|
||||
|
||||
En resumen, creemos que nuestra plataforma ha tenido mucho éxito este mes y estamos seguros de que siguiendo estas recomendaciones podremos lograr nuestras metas a corto y largo plazo.
|
||||
|
||||
|
||||
## :beginner:Anexos
|
||||
|
||||
1. https://hackmd.io/gbfcNdtPTNy4jz60-8Fqpw?view
|
||||
2. https://decentralizedclimate.org
|
||||
3. https://hackmd.io/ARL7nmX7TL2f1FvKKx4olg?both
|
||||
4. https://hackmd.io/5TTxd6x6Qdi9pzRkFq6T7A
|
||||
5. https://hackmd.io/LKrbBs0JSDe0fY25IJ9cjg
|
||||
6. https://nextcloud.neetsec.com/index.php/s/MbSsF52fNMwsDp3
|
||||
|
||||
Creado por Omar Octavio Huerta Valdez.
|
Loading…
Reference in New Issue